Skip to content
MWH-White_Tagline-e1623338861383

Tres Rios Wastewater Reclamation Facility

    Complete
    Ahead of Schedule
    Under Budget
    CLIENT
    Pima County Regional Wastewater Reclamation District (RWRD)
    CLIENT TYPE
    Municipal
    DELIVERY METHOD
    Construction Manager at Risk (CMAR, CM/GC)
    Location
    Tuscon, AZ
    START DATE
    May 2008

    MWH was the CMAR for this plant expansion centered on a 50 million gallons a day (MGD) liquids and solids train replacement. The project also included the construction of a new 37.5mgd, five-stage Bardenpho treatment process by upgrading three 12.5 MGD 3-stage Bardenpho processes and constructing a new 12.5 MGD basin. This project also involved two digesters, a blower building, a primary clarifier, two new aeration tanks, five new secondary clarifiers, three new centrifuges, and a new gravity belt thickener building.

    MWH managed preconstruction, GMP development, and general contracting services during construction. In addition, MWH self-performed over 43% of complex aspects of the work to control the critical path, including procurement, installation of process mechanical piping and equipment, six miles of yard piping, instrumentation and control, and commissioning and startup.

    MWH created 4D BIM to verify site logistics, yard operations, and temporary facilities. By reviewing the schedule in a rich, visual format, our team made sound decisions based on multiple sources of accurate real-time information. As the design changed, the model automatically identified the changes and their respective impact on the project’s critical path and overall delivery. MWH used 5D BIM to monitor the project’s construction cost throughout the design, rapidly generating an array of essential estimating information, including materials quantities and costs, size and area estimates, and productivity projections.

    To ensure the existing functionality of the plant remained fully operational as required, MWH developed over 450 MOPOs to complete 250 mechanical tie-ins, 350 electrical switchover ties, and three plant shutdowns without incident. The entire project, including construction commissioning and startup, was completed while maintaining a fully operational plant.

    project partners
    Jacobs Engineering, McDade Woodcock, Borderland Construction Company, CH2M Hill, Santa Rita Landscaping, Kiewit Infrastructure West Co.
    "I would like to give my sincere recommendation of the MWH team for completing this work on time and on budget. The project team was responsive to our needs and worked in partnership with our organization to ensure our goals were being met. The resulting product will serve our users well and is a high-quality facility that we are proud of."
    Jamie Rivera
    Program Manager, Pima County RWRD

    Awards

    2014 American Public Works Association, Arizona Chapter Public Works Project of the Year
    2013 Metropolitan Pima Alliance Common Ground Award for Partnering